SaskPower grants $95M contract to finish operations hub at GTH (2024)

The total project has been contracted at a $195-million cost, expected to be fully complete by 2026.

Author of the article:

Regina Leader-Post

Published Aug 12, 20242 minute read

Join the conversation
SaskPower grants $95M contract to finish operations hub at GTH (1)

SaskPower has announced that the concluding work on a new operations centre at the Global Transportation Hub (GTH) in Regina is now underway with a contractor selected to finish the project’s second phase.

PCL Construction has been awarded a contract, valued at $95 million, to conduct the work on the second part of the Regina Operations and Maintenance Complex (ROMC).

Advertisem*nt 2

Story continues below

This advertisem*nt has not loaded yet, but your article continues below.

SaskPower grants $95M contract to finish operations hub at GTH (2)

THIS CONTENT IS RESERVED FOR SUBSCRIBERS ONLY

Subscribe now to read the latest news in your city and across Canada.

  • Unlimited online access to articles from across Canada with one account.
  • Get exclusive access to the Regina Leader-Post ePaper, an electronic replica of the print edition that you can share, download and comment on.
  • Enjoy insights and behind-the-scenes analysis from our award-winning journalists.
  • Support local journalists and the next generation of journalists.
  • Daily puzzles including the New York Times Crossword.

SUBSCRIBE TO UNLOCK MORE ARTICLES

Subscribe now to read the latest news in your city and across Canada.

  • Unlimited online access to articles from across Canada with one account.
  • Get exclusive access to the Regina Leader-Post ePaper, an electronic replica of the print edition that you can share, download and comment on.
  • Enjoy insights and behind-the-scenes analysis from our award-winning journalists.
  • Support local journalists and the next generation of journalists.
  • Daily puzzles including the New York Times Crossword.

REGISTER / SIGN IN TO UNLOCK MORE ARTICLES

Create an account or sign in to continue with your reading experience.

  • Access articles from across Canada with one account.
  • Share your thoughts and join the conversation in the comments.
  • Enjoy additional articles per month.
  • Get email updates from your favourite authors.

Sign In or Create an Account

or

View more offers

Article content

“Phase 2 of the ROMC project will provide centralized accommodations for SaskPower’s transmission, distribution and safety groups, which will improve efficiency and overall site access,” stated SaskPower president and CEO Rupen Pandya in a news release Monday.

The project will “centralize operations and reduce operating costs through lower maintenance requirements,” he continued.

Announced in 2021, SaskPower said consolidating six of its 13 offices into this new facility was a solution to aging infrastructure and to streamline operations.

In tandem with the new complex, SaskPower has also committed $4.5 million to purchase a building at 2101 Scarth St. and $120 million for a five-year renovation plan at its headquarters on Victoria Avenue.

Phase 1 of the new facility cost $100 million and began in 2021. It was completed earlier this year. Fleet, metering services and several logistics groups have already relocated there. The second phase will see the addition of warehousing, distribution and transmission operations.

More than 800 employees are expected to be based out of the GTH facility once fully complete, about half the Crown corporation’s payroll.

Advertisem*nt 3

Story continues below

This advertisem*nt has not loaded yet, but your article continues below.

Article content

Construction on Phase 2 is expected to conclude in 2026. PCL anticipates the contract will bring in as many as 150 workers on site.

Recommended from Editorial

  1. SaskPower, SRC join nuclear energy not-for-profit group
  2. GTH drops lawsuit against Sask. mall developer Brightenview

Minister responsible for SaskPower Dustin Duncan has said the consolidation to one hub will save about $1 million every year in operating costs and improve service delivery for SaskPower customers.

In contrast, the Saskatchewan NDP has critiqued the project since its inception, claiming in 2021 that government was leveraging the Crown to fill land space at the GTH, which was floundering at the time the facility was first announced.

Then-leader Ryan Meili called the Crown’s use of 110 acres of land at the transport hub a way to “provide cover for a failed project,” which then-minister responsible for the GTH Don Morgan disputed.

As of 2023, the GTH Authority has sold 1,010 acres of land to tenants since the hub was completed in 2010, with 497 acres still available.

Most recent transactions include a five-acre purchase by trucking company Cam Transport, another 15 acres by 4Tracks, and a $38-million deal with Cargill to house a planned canola crush plant that broke a dry spell for the hub authority.

A news release from Cargill in July said the plant has reached the halfway point in its construction and plans to open in 2025.

The Regina Leader-Post has created anAfternoon Headlinesnewsletter that can be delivered daily to your inbox so you are up to date with the most vital news of the day.Click here to subscribe.

With some online platforms blocking access to the journalism upon which you depend, our website is your destination for up-to-the-minute news, so make sure to bookmark leaderpost.com and sign up for our newsletters so we can keep you informed. Click here to subscribe.

Article content

Comments

You must be logged in to join the discussion or read more comments.

Create an AccountSign in

Join the Conversation

Postmedia is committed to maintaining a lively but civil forum for discussion. Please keep comments relevant and respectful. Comments may take up to an hour to appear on the site. You will receive an email if there is a reply to your comment, an update to a thread you follow or if a user you follow comments. Visit our Community Guidelines for more information.

Trending

  1. Roughriders fall to Alouettes 27-24 on Friday night
  2. Hockey academy's petition asks city council to stay out of Brandt Centre dispute
  3. Effort to add accessible elevator for Wascana Pool waterslides ends with no bids
  4. Smoky conditions threaten Saskatchewan Roughriders game
  5. Sask. COVID-19 restrictions case arrives at Supreme Court's doorstep

Read Next

Latest National Stories

    SaskPower grants $95M contract to finish operations hub at GTH (2024)

    References

    Top Articles
    Latest Posts
    Article information

    Author: Chrissy Homenick

    Last Updated:

    Views: 5488

    Rating: 4.3 / 5 (74 voted)

    Reviews: 89% of readers found this page helpful

    Author information

    Name: Chrissy Homenick

    Birthday: 2001-10-22

    Address: 611 Kuhn Oval, Feltonbury, NY 02783-3818

    Phone: +96619177651654

    Job: Mining Representative

    Hobby: amateur radio, Sculling, Knife making, Gardening, Watching movies, Gunsmithing, Video gaming

    Introduction: My name is Chrissy Homenick, I am a tender, funny, determined, tender, glorious, fancy, enthusiastic person who loves writing and wants to share my knowledge and understanding with you.